All blogs

Add or Update Project Parties / Project Team Members

5 min read

This process shows how to add or update project parties and project team members in Oracle Fusion Cloud Project Financial Management. It is used when a project needs new people assigned to it, or when existing assignments must be changed or removed. You begin by finding the project from the My Projects screen, then open Manage Project Resources from the Task pane. There you add a resource, choose the person and project role, set the From and To dates, and save. You finish by reviewing the Project Overview to confirm the team is correct.

Process steps

  1. Step 1

    Hello, this video covers the process of adding or updating project parties and project team members in Oracle Fusion Cloud Project Financial Management.
    Add or Update Project Parties / Project Team Members: step 1
  2. Step 2

    Once logged in, click on the Home icon to navigate to the home page.
    Add or Update Project Parties / Project Team Members: step 2
  3. Step 3

    From the home page, click the arrow button on the navigation bar to navigate to the Projects menu.
    Add or Update Project Parties / Project Team Members: step 3
  4. Step 4

    Once the menu expands, click on the Projects menu to access project management functions.
    Add or Update Project Parties / Project Team Members: step 4
  5. Step 5

    From the Projects menu, click on the Project Financial Management sub-menu to begin searching for projects.
    Add or Update Project Parties / Project Team Members: step 5
  6. Step 6

    Once on the My Projects screen, click on the Project Name or Number field to search for the required project.

    Add or Update Project Parties / Project Team Members: step 6
  7. Step 7

    In the search field, enter the Project Name or Number in the designated field and select the desired project from the List of Values that appears.
    Add or Update Project Parties / Project Team Members: step 7
  8. Step 8

    After entering the project details, click the Search icon to execute your search query.
    Add or Update Project Parties / Project Team Members: step 8
  9. Step 9

    From the search results, click on the Project Name Hyperlink to which you want to add or update the Parties or Team Members.
    Add or Update Project Parties / Project Team Members: step 9
  10. Step 10

    Once the project menu appears, click on the Project Name hyperlink and select Manage Financial Project Settings to proceed with managing project resources.

    Add or Update Project Parties / Project Team Members: step 10
  11. Step 11

    In the Manage Financial Project Settings page, click the Task pane on the right-hand side to access additional project management tasks.
    Add or Update Project Parties / Project Team Members: step 11
  12. Step 12

    From the Task pane, select the Manage Project Resources task option to begin managing project team members.
    Add or Update Project Parties / Project Team Members: step 12
  13. Step 13

    Once on the Manage Project Resources page, click on the Add Resource button to include additional project team members.
    Add or Update Project Parties / Project Team Members: step 13
  14. Step 14

    In the Add Resource dialog, click on the Dropdown button next to the Resources field to search for team members.
    Add or Update Project Parties / Project Team Members: step 14
  15. Step 15

    From the Resources dropdown, click on the Search button to open the resource search window.
    Add or Update Project Parties / Project Team Members: step 15
  16. Step 16

    In the resource search window, note that you can search for the person using parameters such as name or email.
    Add or Update Project Parties / Project Team Members: step 16
  17. Step 17

    To search for a team member, click on the Name field and enter the team member's name you wish to add.

    Add or Update Project Parties / Project Team Members: step 17
  18. Step 18

    After entering the member's name, click on the Search button.
    Add or Update Project Parties / Project Team Members: step 18
  19. Step 19

    From the search results, select the appropriate resource you want to add as a project team member.
    Add or Update Project Parties / Project Team Members: step 19
  20. Step 20

    Once the resource is selected, click on the OK button to confirm your choice and return to the Add Resource screen.
    Add or Update Project Parties / Project Team Members: step 20
  21. Step 21

    Back on the Add Resource screen, click on the dropdown arrow next to the Project Role field.
    Add or Update Project Parties / Project Team Members: step 21
  22. Step 22

    From the Project Role dropdown, select the designated role assigned to the resource in the previous step.
    Add or Update Project Parties / Project Team Members: step 22
  23. Step 23

    To specify the team member's start date, click on the Calendar icon next to the From Date field to set the start date.
    Add or Update Project Parties / Project Team Members: step 23
  24. Step 24

    From the calendar, select the From Date to specify when the team member's participation begins.
    Add or Update Project Parties / Project Team Members: step 24
  25. Step 25

    To specify the team member's end date, click on the Calendar icon next to the To Date field to set the end date.
    Add or Update Project Parties / Project Team Members: step 25
  26. Step 26

    From the calendar, select the To Date.
    Add or Update Project Parties / Project Team Members: step 26
  27. Step 27

    Once the dates are selected, you will notice that Effort Hours will be calculated automatically based on the From and To dates you have selected.
    Add or Update Project Parties / Project Team Members: step 27
  28. Step 28

    After entering all the required information, click the Save and Close button to save the team member and return to the project resources screen.
    Add or Update Project Parties / Project Team Members: step 28
  29. Step 29

    Back on the project resources screen, confirm that the team member has been successfully created and added to the project.
    Add or Update Project Parties / Project Team Members: step 29
  30. Step 30

    To manage existing team members, click on the dropdown button for the team member to view available options.
    Add or Update Project Parties / Project Team Members: step 30
  31. Step 31

    From the dropdown menu, note that you can alter the details for any team member, including updating existing information, replacing them with another member, or removing them from the project entirely.
    Add or Update Project Parties / Project Team Members: step 31
  32. Step 32

    To view the complete project team, click the Task pane on the right-hand side to access additional viewing options.

    Add or Update Project Parties / Project Team Members: step 32
  33. Step 33

    From the Task pane, select the Project Overview task to view comprehensive project information.
    Add or Update Project Parties / Project Team Members: step 33
  34. Step 34

    Once on the Project Overview page, review the Project Team Members' details in the Overview section to verify all team member assignments.
    Add or Update Project Parties / Project Team Members: step 34
  35. Step 35

    Once reviewed, click on the Done button to finalize the process and return to the Project Financial Management page.
    Add or Update Project Parties / Project Team Members: step 35
  36. Step 36

     Thank You! In this video, you learned how to add or update project parties and project team members in Oracle Fusion Cloud Project Financial Management.
    Add or Update Project Parties / Project Team Members: step 36

Start a conversation

Tell us where user enablement fits into your Oracle delivery.